New Tank Construction – Growing Client’s Inventory Capacity
An addition to their site in Central Alberta, meant this clients overall storage capacity at their rail terminal would be more than…
An addition to their site in Central Alberta, meant this clients overall storage capacity at their rail terminal would be more than…
This 70,000 bbl tank moved from concept to completion in just over (3) months. Due to market volatility in 2020, the client…
With where this tank was located on the client’s property, our crew had to navigate tight and congested working conditions for the…
Customer required an 8500 MT (30,000BBL) molten sulphur tank to be constructed. Elite Integrity Services executed a large scale turnkey operation on…
Elite Integrity Services was recently contracted to complete an entire tank replacement project inside our clients 5-day turn around window. Working closely…
A large expansion to an existing facility in Northeast British Columbia including (8) tanks of varying sizes to be constructed within the…
This project was executed in a remote desert location with extremely hot temperatures and nearby forest fires. The crews were challenged to…
This new 70,000 bbl gasoline storage tank was constructed in the middle of a highly congested, fully operational facility in Northeastern British…
Working with our client at the onset to understand their needs, Elite was able to design, construct, and safely execute this project…
The 115,576 BBL multi-bay, storage tank went from mobilization to mechanically complete in just over two and a half months. Tank construction included a…
This project included the construction of (3) new tanks to be built in Central Alberta. The tanks all required hydro-testing, external painting,…
Three 30,000 bbl tanks required completion in a compressed schedule. Working with operations a revolving schedule was developed to accommodate continuous construction…
Three 30,000 bbl tanks required completion in a compressed schedule. Working closely with operations, a revolving schedule was developed to accommodate continuous…
To support expanding infrastructure of its assets, Elite’s client required the construction of a 100,000 bbl and 10,000 bbl storage tank at…
Elite’s client required three new tanks constructed in a short schedule. In five months, Elite successfully completed and turned over three 40,000…
Due to environmental conditions at site Elite worked with their client to fabricate structural steel skids for tank foundations in lieu of…
Working with the client it was determined that a structurally supported roof was not suitable for the tank operation. Elite engineered, pre-fabricated…
Due to the remote location special considerations were made to ensure the crew had suitable accommodations and attention was paid to work…
The 122,827BBL tank went from mobilization to mechanical completion in just over two and a half months. Working in close proximity with…
Six 10,000 bbl tanks required completion in a compressed schedule. Working with operations a revolving schedule was developed to accommodate continuous construction…