Field Tank Construction
New Tank Construction – Multi Tank Project
Three 30,000 bbl tanks required completion in a compressed schedule. Working with operations a revolving schedule was developed to accommodate continuous construction and mitigate schedule loss with the challenging climate conditions, including severe winter conditions and freezing temperatures.
Project Highlights:
• 24” diameter, coated large internal piping assemblies.
• Great communication with client and EPC to expedite project approval processes.
• (4) months to complete the tanks including the installation of Sandborn Internal Floating Roofs.
• Challenging winter conditions.
- Project Size: (1) 67’-0” Diameter x 48’-0” High & (2) 77’-0” Diameter x 36’-0
- Project Type: New Construction
- Completion Date: January 2019
- Service: Condensate & High and Low Sulphur Crude Storage Tanks
More Projects
New Fuel Distribution Facility
Three 30,000 bbl tanks required completion in a compressed schedule. Working with operations a revolving schedule was developed to accommodate continuous construction…
70,000 Barrels of Increased Gasoline Storage
Three 30,000 bbl tanks required completion in a compressed schedule. Working with operations a revolving schedule was developed to accommodate continuous construction…
Pulp Mill Turnaround Project
Three 30,000 bbl tanks required completion in a compressed schedule. Working with operations a revolving schedule was developed to accommodate continuous construction…
Turnkey Operations On A Liquid Sulphur Tank – Central AB
Three 30,000 bbl tanks required completion in a compressed schedule. Working with operations a revolving schedule was developed to accommodate continuous construction…
Tank Repair – Major Foundation Remediation & Tank Floor Replacement
Three 30,000 bbl tanks required completion in a compressed schedule. Working with operations a revolving schedule was developed to accommodate continuous construction…