Field Tank Construction
New Tank Construction – Large Diameter & Expedited Schedule
The 115,576 BBL multi-bay, storage tank went from mobilization to mechanically complete in just over two and a half months. Tank construction included a spiral staircase, rooftop platform and a multi-inlet fire foam suppression system. Our team worked closely with our client and coating sub-contractor to complete the external painting in sub-zero temperatures.
Project Highlights:
- Our crew completed this project safely, ahead of schedule and with zero weld repairs
- Special coating additives were used for sub zero external painting
- Project Size: (1) 131’-3” Diameter x 48’-0” High
- Project Type: New Construction
- Completion Date: October 2019
- Service: Diesel
More Projects
New Tank Construction – Growing Client’s Inventory Capacity
The 115,576 BBL multi-bay, storage tank went from mobilization to mechanically complete in just over two and a half months. Tank construction included a…
New Tank Construction – Executing Best in Quality Control
The 115,576 BBL multi-bay, storage tank went from mobilization to mechanically complete in just over two and a half months. Tank construction included a…
Tank Repair – Client Needed an Elite Solution
The 115,576 BBL multi-bay, storage tank went from mobilization to mechanically complete in just over two and a half months. Tank construction included a…
Tank Repair – Floor Replacement & Major Foundation Installation
The 115,576 BBL multi-bay, storage tank went from mobilization to mechanically complete in just over two and a half months. Tank construction included a…
New Tank Construction – Multiple Tanks c/w Concrete Ring Walls
The 115,576 BBL multi-bay, storage tank went from mobilization to mechanically complete in just over two and a half months. Tank construction included a…